Nearly 1,985 GW of new power capacity waits to connect to the U.S. electric grid, more than the nation's entire generating fleet.
The backlog reflects not a shortage of energy projects, but an interconnection process that is the primary constraint on the grid, slowing the clean energy buildout the country counts on.
Texas alone accounts for 440 GW, or 22% of the national queue, while California adds 189 GW and Arizona another 118 GW, revealing that America's greatest energy challenge is no longer generating power, but connecting it.
The future of the grid is built, waiting in queue to power the scientists, entrepreneurs, and dreamers, shaping tomorrow.
| Category | Value (GW) |
|---|---|
| Texas | 440.1 |
| California | 189.3 |
| Arizona | 118.4 |
| Oregon | 108.2 |
| Illinois | 81.2 |
| Nevada | 67.9 |
| Indiana | 65.6 |
| Michigan | 58.5 |
| Oklahoma | 57 |
| Washington | 55.1 |
| Colorado | 49.8 |
| Utah | 43 |
| Georgia | 42.7 |
| Arkansas | 42.3 |
| Louisiana | 40.8 |
| New Mexico | 37.9 |
| Kansas | 35.9 |
| Missouri | 30 |
| Virginia | 30 |
| Minnesota | 29.3 |
| New York | 27.2 |
| Wisconsin | 26.5 |
| Iowa | 22.5 |
| Kentucky | 21.5 |
| Florida | 20.8 |
| Ohio | 20.5 |
| South Carolina | 20.5 |
| Wyoming | 19 |
| Mississippi | 18.5 |
| North Carolina | 18.2 |
| Idaho | 16.5 |
| Nebraska | 16 |
| North Dakota | 14.8 |
| New Jersey | 14.4 |
| Tennessee | 14.2 |
| Pennsylvania | 13.2 |
| Montana | 12.8 |
| Massachusetts | 11.2 |
| Alabama | 9 |
| South Dakota | 8.6 |
| Maryland | 6.7 |
| West Virginia | 5.8 |
| Maine | 1.2 |
| Rhode Island | 1 |
| Connecticut | 0.7 |
| Delaware | 0.5 |
| New Hampshire | 0.1 |
| Vermont | 0.1 |